Written by Adaptive US | 11/24/26, 9:01 AM

The BRD is signed. Stakeholders have approved 140 requirements, the traceability matrix is clean, and the sponsor asks the question you knew was coming: "So what will this cost?" Most business analysts hand the document to two or three vendors at this point and wait. That's a mistake, because the quotes that come back will be priced on the vendor's reading of your requirements, not yours.

A vendor doesn't price a BRD. They price hours, licenses, and risk, and they get there by translating each requirement into work. If you do that translation first, you control the conversation: you know which lines are expensive, why they're expensive, and which ones the business could live without. This guide walks through that translation step by step, using an ERP rollout as the example.

What a Vendor Actually Prices When They Read Your BRD

Open any ERP quote and you'll find the same handful of cost buckets, whatever the platform. Your requirements feed every one of them, but not equally.

  • Licensing or subscription. Usually priced per user per month for cloud ERPs, so your user count from the stakeholder analysis matters more than most BAs expect.
  • Configuration. Setting up standard modules: chart of accounts, warehouses, approval rules, tax settings, document templates.
  • Customization. New code: custom fields with logic behind them, new workflows, reports the standard tool can't produce.
  • Data migration. Extracting, cleansing, mapping, and loading data from the old system.
  • Integrations. Connections to e-commerce, banking, payroll, CRM, or anything else that has to exchange data with the ERP.
  • Training, UAT support, and hypercare. The weeks before and after go-live when users need hands-on help.
  • Master data. Customers, vendors, products, chart of accounts. Usually required, often messy. Ask how many duplicates exist before anyone commits to a number.
  • Open transactions. Unpaid invoices, open sales and purchase orders, current stock levels. These must balance to the penny at cutover, so they need reconciliation effort.
  • History. Closed transactions from prior years. This is the layer stakeholders ask for and rarely need inside the new system. An archived read-only database or a reporting extract is often enough, and it can remove weeks from the plan.
  • 95 are fits or configurations, totaling about 40 days of effort.
  • 40 are integrations and migration objects, totaling about 45 days.
  • 5 are customizations, totaling about 35 days.
  • Run a requirement-level fit-gap and sort every row into fit, configuration, workaround, or customization.
  • Size migration by layer and write a short spec for each integration, so vendors aren't pricing assumptions.
  • Apply MoSCoW by effort, push expensive Coulds to phase 2, and ask vendors to price each priority band separately.

Here's the thing: a BRD written in business language doesn't tell the vendor which bucket a requirement lands in. "The system must track customer credit limits" might be a checkbox in the sales module or three weeks of development. The vendor will assume the worse case unless you show otherwise, and that assumption ends up in the price.

Run the Fit-Gap Before Anyone Talks Money

A fit-gap analysis compares each requirement against what the ERP does out of the box. You've probably done one for a system selection; for estimating, you need a more granular version, one row per requirement, tied back to the BRD through your traceability matrix.

Sort every requirement into one of four categories:

  1. Fit. The standard module handles it as delivered. Cost is close to zero beyond setup.
  2. Fit with configuration. The feature exists but needs settings, rules, or templates. Cost is measured in hours.
  3. Gap, workaround acceptable. The system can't do it exactly, but a process change gets the business most of the way there. Cost is mostly change management and training.
  4. Gap, customization required. Only new code closes it. Cost is measured in days or weeks, plus ongoing maintenance.

The hardest conversations happen in category three. Stakeholders often describe their as-is process as a requirement ("approvals go to Maria, then to the CFO"), when the real need is a to-be outcome ("purchases over a threshold get two approvals"). Rewriting those requirements around outcomes moves a surprising number of rows from category four to category two. Run elicitation sessions specifically for this; walk each gap past the process owner and ask what would break if the system did it the standard way.

Once your rows are sorted, count them and attach rough effort ranges. Before vendor quotes come back, it also helps to have an outside number to hold your tallies against. If Odoo is on the shortlist, a published breakdown of odoo implementation cost that starts from user count, the functional areas in scope, and your current system gives you a reference range to sanity-check your own estimate. Treat a tool like that as a cross-check, not a quote; your fit-gap is still the source of truth.

Configuration vs. Customization: Where the Budget Splits

In my experience, the widest swings between ERP quotes come from one line: where configuration ends and customization begins. Configuration uses tools the vendor already supports and upgrades. Customization creates code that someone has to write, test, document, and re-test every time the platform releases a new version.

That last point is why customization costs more than its build hours suggest. A custom workflow that takes a week or two to build also needs regression testing at every major upgrade, for as long as you run the system.

The licensing model can shift this line too. Odoo is a useful example: the Community edition is free and open source, while the paid Enterprise plans are billed per user per month. On Odoo's own pricing page, the Studio customization tool, multi-company support, and external API access sit only in the higher Custom plan, not in Standard. So a single requirement like "sync orders from our web store through the API" can change the subscription tier for every user, not just add integration hours. That's exactly the kind of dependency your estimate should surface.

Use a table like this to show stakeholders how requirement types map to cost:

Requirement type

Example

Main cost driver

Typical effort signal

Standard fit

Issue invoices in multiple currencies

Setup and testing

Hours

Configuration

Two-step approval on purchases over $10,000

Consultant time

Hours to a few days

Custom field with logic

Auto-calculate landed cost per SKU

Development plus upgrade testing

Days

Custom workflow or report

Bespoke commission calculation for sales reps

Development, testing, maintenance

Weeks

Integration

Nightly bank statement import

Connector or API work, error handling

Days to weeks

Data migration object

Open purchase orders from the legacy system

Mapping, cleansing, test loads

Days per object


Add a column for the BRD requirement ID and this table doubles as a traceability artifact. Sponsors respond to it far better than to a total number, because they can see where the money goes.

Sizing Data Migration and Integrations

Migration and integrations are where estimates drift most, because both depend on things the BRD rarely describes: the state of the old data and the behavior of other systems.

For migration, split the scope into three layers and size each one separately:

For integrations, write one short spec per connection: direction (one-way or two-way), frequency (real-time, hourly, nightly), volume, and who owns the other system. An e-commerce sync that runs every five minutes in both directions is a different project from a nightly payroll export. If you can't answer these questions yet, flag the integration as an assumption in the estimate rather than leaving the vendor to guess.

Where MoSCoW Changes the Final Number

MoSCoW prioritization was devised by Dai Clegg at Oracle in 1994 for timeboxed development, and it's still the most practical way to turn a requirements list into budget options. The key guidance comes from DSDM, which recommends keeping Must Have work to no more than 60% of total effort, with Could Haves around 20%. Notice that the rule measures effort, not the number of requirements.

That distinction matters for ERP budgets. Suppose your fit-gap gives you 140 requirements:

That's 120 days in total. If all five customizations are labeled Must, along with most of the configurations and integrations, Must Have effort easily passes 60% of those 120 days, and the project has almost no contingency. Now walk through those five with the business. Say one is a bespoke commission report that finance could produce from an export for the first six months. Moving it to Could and scheduling it for phase 2 doesn't just save its build days. It removes its testing, its upgrade maintenance, and its share of training from the phase 1 budget.

Run this exercise before quotes arrive, then send vendors a BRD where every requirement carries its MoSCoW label. Ask them to price Musts and Shoulds separately from Coulds. You'll get a base price and a list of optional extras, which gives your sponsor real choices instead of a single take-it-or-leave-it figure.

Before You Send the BRD Out

Pricing an ERP rollout is a BA job, not something that happens after the BA job ends. Three moves make the biggest difference:

Do that, and the quotes you receive will be comparable, explainable, and much harder to inflate.

FAQ

Should the BA or the vendor run the fit-gap analysis?

Both, ideally. As a Business Analyst do your own first pass using demos and documentation, then ask the shortlisted vendors to confirm or challenge each row. Differences between your fit-gap and theirs are the most useful thing a pre-sales session can produce.

How detailed does a requirement need to be for a vendor to price it?

Detailed enough to place it in one of the four fit-gap categories. Acceptance criteria help most: "approvals required over $10,000" can be priced, while "flexible approvals" can't.

What if stakeholders insist every requirement is a Must?

Show them the effort split. When Must Have work exceeds the 60% guideline, ask which items the business could operate without for the first three months. Framing it as phase timing, rather than cutting scope, usually unlocks the conversation.